Developer claims DIA terminal change orders will cost $151M

Written by on June 16, 2019

The developer of Denver International Airport‘s Great Hall Project says in confidential documents obtained by CBS4 that change orders covering everything from toilet partitions, to wall coverings and escalator relocation will account for an additional $151 million dollars in costs. That is nearly half of the projected $311 million cost overrun on the project. Up until now, the City of Denver has emphasized delays and increased costs for the project emanated mainly from terminal concrete that was found to be weaker than expected. 